Factory Inspection for EPC Projects: ITPs, Hold Points and Expediting in China
How factory inspection works on EPC projects buying equipment from China: inspection and test plans, hold and witness points, vendor documents, expediting and release for shipment.
By Packsel Consulting, Purchasing insights
Article date: · 4 min read
Updated:
On an EPC project, factory inspection of equipment bought from China is usually run against an inspection and test plan (ITP) that the supplier submits and the contractor approves, with hold points the factory cannot pass without the contractor’s inspector, witness points the inspector may attend, and a release note issued before the equipment ships. The inspector’s job is to check each point on the plan, record the results, and raise non-conformances while they can still be fixed at the factory.
Engineering, procurement and construction (EPC) contractors buy pumps, skids, steel structures, pressure equipment, switchgear and other items for projects with fixed schedules and strict specifications. Getting equipment right at the factory is far cheaper than fixing it on site.
Start with the inspection and test plan
The ITP lists every inspection and test for an item in production order, from incoming materials to final packing. For each step it shows:
- What is checked, and against which specification or drawing.
- The acceptance criteria.
- Who performs the check, and which records are produced.
- The inspection status for the contractor and any third party.
The supplier usually prepares the ITP and submits it for approval with the other vendor documents. Review it carefully: an ITP that leaves out a test the specification requires is a common source of disputes later.
Hold, witness and review points
ITPs commonly mark each step with one of these:
- Hold point (H): production cannot proceed past this step until the contractor’s inspector has attended or formally waived it. Typical hold points include hydrostatic tests, final functional tests and the final inspection before release.
- Witness point (W): the inspector is notified and may attend; if they don’t, production can continue.
- Review point (R): the inspector reviews the records rather than attending.
Agree the notice period for each type, often several working days, and who in the factory issues the notifications. Missed notifications are a frequent cause of rejected tests.
Hold a pre-inspection meeting
Before production starts, a pre-inspection meeting (PIM) or kick-off with the supplier confirms the ITP, the latest drawing revisions, the material certificates required, the inspection schedule and the contacts on both sides. It is the cheapest point to clear up misunderstandings.
Review vendor documents alongside inspection
EPC packages require documents as well as equipment: drawings, calculations, material certificates, welding procedures and qualifications, test procedures, NDT reports, manuals and spare parts lists. These are usually tracked in a vendor document register. Inspection and document review support each other: a hydrotest can’t be released without the approved test procedure and calibrated gauges.
Expediting: keep the schedule visible
Expediting tracks progress against the delivery schedule: material orders, sub-supplier deliveries, fabrication, painting, testing and packing. Regular expediting visits or reports give the contractor early warning when a critical item is slipping, while there is still time to act.
Non-conformances and release
When an inspection finds a deviation, the inspector raises a non-conformance report (NCR) describing the requirement, the finding and the evidence. The supplier proposes a correction, the contractor approves it, and the inspector checks it is done. When every hold point is passed and every NCR closed or accepted, the contractor issues a release note or inspection release certificate, and the equipment can ship.
Packing and preservation
Check export packing, preservation for long storage, marking and the packing list before release. Equipment may sit in a laydown yard for months before installation. See crating and shipping heavy equipment.
How we support EPC inspection in China
When we act for a contractor, we review the supplier’s ITP against the specification before production, attend the pre-inspection meeting, and attend hold and witness points against the approved plan. We record measured results rather than ticks, raise NCRs with evidence, and follow each one until it is closed. Between visits we expedite against the schedule and report progress in the contractor’s format.
How Packsel Consulting can help
We provide on-site inspection, factory acceptance testing attendance and production oversight for contractors buying equipment in China and across Asia. Specialist testing and certification are performed by qualified bodies, which we can arrange or witness.
Talk to us about an order. Tell us the equipment, the supplier, the ITP status and the delivery schedule.
About these articles
Packsel Consulting
Purchasing insights · U.S. and Hong Kong
Practical guidance for U.S. businesses buying from Asia.
How we work