A factory acceptance test (FAT) allows buyers to assess equipment against an agreed protocol while it remains at the manufacturer’s facility. For machinery that cannot readily be sampled, this is an important opportunity to document performance and identify outstanding work before shipment.

What a FAT is

A FAT is a planned test of the finished equipment at the manufacturer’s plant, run to a written protocol and witnessed by the buyer or someone acting for them. It is followed later by a site acceptance test (SAT) after installation at your facility.

The FAT should prove the equipment meets the specification as far as possible without your site, your materials or your utilities.

Write the protocol before you sign the order

Agree the FAT protocol as part of the purchasing documentation, well before the equipment is ready to ship. It should state:

  • Scope: which machines, options and accessories are tested
  • References: the specification, drawings and component list, each with a revision number
  • Tests: each test, the method, the acceptance criterion and who records the result
  • Conditions: power supply, air, water, materials, and who provides test materials
  • Duration: for production equipment, a continuous run of an agreed length to catch problems that only show up once the machine is warm
  • Documents to be delivered: manuals, electrical drawings, PLC programs and backups, spare parts list, certificates
  • What happens on failure: the fix and the re-test, and who pays for travel if a second visit is needed

Typical content

Area Examples of checks
Visual and dimensional Build quality, guarding, welds, paint, overall dimensions, nameplates
Components Brand and model of motors, drives, PLC, hydraulic and pneumatic parts against the agreed list
Electrical Panel build, wiring labels, earth bonding, voltage and frequency for U.S. supply
Safety E-stops, interlocks, guards, light curtains, lockout points
Performance Speed, output rate, accuracy or repeatability, measured, not stated
Endurance Continuous run with no faults over the agreed time
Documentation Manuals in English, drawings, software, spare parts list

Check the electrical side carefully. Equipment built for 380V 50Hz needs to be built for your U.S. supply, and U.S. sites and insurers may expect the control panel to be built to U.S. standards such as UL 508A or NFPA 79. Agree this at the specification stage; it is hard to change at FAT.

Witnessing it

The witness should follow the protocol line by line, record actual values rather than ticking “OK,” photograph and film the key tests, and refuse to sign off tests that weren’t done. A punch list of open items is normal. Each open item should identify the required action, responsible party and completion date.

If nobody can travel, a remote FAT over live video can work for simpler equipment. Send the protocol in advance, ask for a second camera on the instruments, and record everything. Some things, like noise, vibration and build quality up close, don’t come across well on video.

Tie payment to the result

A common pattern for capital equipment is a deposit with the order, a large stage payment after a passed FAT, and a final retention after installation and SAT. The FAT payment is your main leverage. Don’t release it with open punch-list items that matter.

If a payment depends on a passed test, agree what evidence releases it before placing the order.

Factory acceptance testing for mining and heavy industrial equipment

Mining equipment, crushers, conveyors and similar heavy equipment raise extra FAT questions:

  • Load: the factory may not be able to run the machine at full load or with real ore. Agree what can be tested and how the rest will be proven at site.
  • Structural checks: weld inspection and non-destructive testing records for frames and wear parts.
  • Wear parts: material certificates and hardness tests for liners, teeth and screens.
  • Safety systems: guarding, emergency stops, pull-wire switches on conveyors, and lockout points.
  • Documentation: maintenance manuals, spare parts lists and lubrication schedules.

Where a full FAT isn’t possible, a partial FAT plus a detailed site acceptance test is common.

How we run a FAT for a client

We send the factory the FAT protocol before the test date and ask them to confirm they can run every item. On the day, we follow the protocol line by line, record the measured values rather than ticking a box, and film the key tests. At the end, we agree a punch list with the factory: each open item, who fixes it, and how it will be checked. Our client receives the results and the punch list the same day, so the payment decision can be made with the evidence in hand.

Packsel Consulting writes FAT checklists with you, witnesses acceptance tests at factories across Asia and follows the punch list through production oversight.

About these articles

Packsel Consulting

Purchasing insights · U.S. and Hong Kong

Practical guidance for U.S. businesses buying from Asia.

How we work
More insights

Get in touch

Tell us what you’re buying.

Send us the product, the supplier if you have one, and your dates. We’ll suggest a scope for one stage or the whole order.