Shipping heavy equipment from Asia: RoRo, flat racks and break bulk

How excavators, cranes, gensets and machinery get from an Asian factory to a U.S. port, and the cleanliness, lashing and paperwork problems that delay them.

By Packsel Consulting, Purchasing insights
Article date: · 4 min read
Updated:

Equipment that exceeds standard container dimensions requires a shipping plan suited to its size, weight and handling requirements. The selected method affects cost, transit arrangements and the preparations needed at the supplier and destination port.

This is a buyer’s overview. Your freight forwarder plans the actual shipment.

The main options

Method Suits Notes
Standard container Small machines, parts, machines that can be partly dismantled Cheapest and most frequent; size limits apply
Open-top container Over-height cargo loaded by crane Tarpaulin cover; still limited in width
Flat rack Over-width or over-height machines Lashed to an open platform; exposed to weather
RoRo (roll-on, roll-off) Self-propelled or towable equipment Driven onto a car-carrier-style vessel; fewer lifts
Break bulk Very large or heavy pieces Lifted aboard individually; project cargo planning

RoRo is often a good fit for excavators, loaders and trucks because the machine is driven on and off, with no container lifts. Equipment that can’t move under its own power can go on roll trailers. Service depends on the route, so ask your forwarder which ports in Asia and the U.S. have RoRo sailings.

Clean means clean

U.S. agricultural inspections look for soil, seeds, plant material and insects on arriving equipment. Machines with soil on tracks, buckets or inside frames can be held, cleaned at your cost or refused. This applies to used machinery especially, but new machines that were tested in a yard can carry soil too.

Used farm machinery has a stricter rule: from a region affected by foot-and-mouth disease, USDA requires an original certificate from the exporting country’s animal health authority confirming the machine was steam-cleaned. Ask your broker whether anything similar applies to your equipment.

Ask the factory to wash and dry the machine before shipment, including tracks, undercarriage, radiator fins and cab floor, and to photograph it. Any wooden blocking or dunnage must meet ISPM 15 and carry the mark.

Preparing the machine

  • Lashing points and certificates: the carrier needs to know the machine’s weight, centre of gravity and lashing points.
  • Fluids and batteries: carriers have rules on fuel levels and battery disconnection. Ask the forwarder.
  • Protection: cover exposed hydraulic cylinder rods, seal openings, protect glass. Corrosion inhibitors and wraps help on flat racks.
  • Loose items: buckets, attachments and spare parts should be listed on the packing list and secured, often in a crate on the machine or in a separate container.
  • Photos at loading: all sides, plates and hour meter, before it leaves your supplier.

Documents

Beyond the usual commercial invoice, packing list and bill of lading, equipment shipments often need the machine’s PIN or VIN on the documents, engine certification paperwork for EPA purposes, and dimensions and weights for every piece. Machines that will be driven on public roads, and trailers, can also come under Department of Transportation rules. Raise this early with your broker.

Once you have a shipping plan, work through the supplier-to-forwarder handoff to assign responsibility for cargo readiness and documents.

At the U.S. end

Plan the move from the port before the machine lands. Oversize road moves need permits and sometimes escorts, and that takes time to arrange. Inspect the machine on arrival, with photos, before signing for it, and note damage on the delivery receipt.

How we prepare equipment for shipping

Before a machine leaves the factory, we check it has been washed after testing, photograph it from all sides with the identification plate visible, and confirm lashing points, weights and dimensions with the forwarder. We list loose items packed with the machine on the packing list.

Packsel Consulting coordinates equipment shipments between your supplier, forwarder and broker as part of shipping coordination, and checks cleanliness and documents at pre-shipment inspection. We don’t carry freight.

About these articles

Packsel Consulting

Purchasing insights · U.S. and Hong Kong

Practical guidance for U.S. businesses buying from Asia.

How we work
More insights

Get in touch

Tell us what you’re buying.

Send us the product, the supplier if you have one, and your dates. We’ll suggest a scope for one stage or the whole order.