First article inspection (FAI) is a full measurement and verification of the first part, or first few parts, made by a new production process, to prove that the process can produce parts that meet every requirement on the drawing. The FAI report lists each requirement and the measured result, and the buyer approves it before production continues.
FAI is common for machined parts, castings, molded parts, and fabricated components.
What an FAI report includes
- A ballooned drawing, with each requirement numbered.
- A table showing each requirement, its tolerance, and the measured value.
- The measuring equipment used.
- Material certificates and process certificates, such as heat treatment and plating.
- Photos of the part.
The aerospace standard AS9102 sets out a widely used FAI format. Many industries use it as a template.
When to request an FAI
- When a new part or new mold goes into production.
- When the drawing changes.
- When production moves to a new supplier, factory, or process.
- After a long break in production.
How FAI differs from other checks
FAI proves the process can make a correct part. It does not prove every later part will be correct. Production still needs in-process checks and pre-shipment inspection.
See also CNC machined parts and first article inspection.
If you need a broader check later in the run, our during-production inspection guide explains where that visit fits.
What to agree with the supplier
Before production, agree:
- Which parts need FAI, and how many pieces are measured.
- The report format, such as AS9102 or the supplier’s own format.
- The measuring equipment and whether it is calibrated.
- That production does not continue until you approve the FAI.
- That a new FAI is required after any change.
How to review an FAI report
- Check every requirement on the drawing has a balloon and a result.
- Look for results at or near the limits of the tolerance.
- Check the material certificates match the specified material.
- Confirm the drawing revision on the report matches the one on your order.
- Compare a few measurements yourself or through an inspector, if possible.
A report where every result is exactly at the nominal value deserves a closer look. Real measurements vary.
FAI for molded and cast parts
For injection molded parts, the FAI is often done on samples from each cavity, because each cavity can produce slightly different parts. For castings, it may include X-ray or sectioning results.
Common problems
- Missing dimensions, especially geometric tolerances.
- Measurements taken with the wrong equipment.
- Reports based on an old drawing revision.
- Production starting before the FAI is approved.
A hypothetical buyer receives an FAI report showing all dimensions in tolerance, but the report uses an older drawing revision. Checking the revision before approval prevents a full production run to the wrong drawing.
How we review FAI reports
When a supplier sends a first article report, we check every drawing requirement has a result, look for results near the tolerance limits, and confirm the drawing revision and material certificates. Where we can, we measure a few critical dimensions on the actual first article parts ourselves, so the client isn’t relying entirely on the supplier’s measurements.
How Packsel Consulting can help
We follow first article approval as part of production oversight and check that the supplier’s measurements are complete and consistent.
Talk to us about an order. Tell us what you are buying, where the supplier is, and which stage you have reached.
About these articles
Packsel Consulting
Purchasing insights · U.S. and Hong Kong
Practical guidance for U.S. businesses buying from Asia.
How we work